Akufo-Addo to commission phase one of Obetsebi Lamptey Interchange today

President Nana Addo Dankwa Akufo-Addo will today, Tuesday, November 24, 2020, commission the first phase of the Obetsebi Lamptey interchange. The President will undertake the exercise as part of his two-day campaign tour of the Greater Accra Region.

The three-tier interchange is a key intersection in the arterial road network in Accra. It is aimed at helping to reduce congestion being experienced by commuters on the stretch. The interchange is part of the Ring Road system and located at the intersection of four major arterials: the Kaneshie Mallam Road (Dr. Kofi Busia Highway), the Ring Road West, Ring Road West Extension and the Graphic Road. The project commenced in October 2019 with a sod-cutting ceremony for completion in 18 calendar months.

According to the Ministry of Roads and Highways, the works have been completed 5 months ahead of schedule. Below is the breakdown of the phases of the project according to the Roads Ministry: Phase I involved the construction of a 550m viaduct and ramps between Graphic Road and Dr. Busia Highway (Kaneshie Mallam Road).

Under the project, a 2 No. (5.5 x 2)m box culvert across the Graphic Road and storm drain of similar size was constructed up to the Ring Road West Carriageway. This storm drain shall be continued up to Mpamprom Junction under Phase II of the project. The storm drainage system is to help address the flooding challenges being experienced at Obetsebi Lamptey.

Also, under Phase II, the 3rd tier of the interchange which would be on the Ring Road West (Awudome to Central Mosque at Abbosey Okai) will be constructed. Additionally, the following road works shall be undertaken;Widening of the Ring Road West (from Awudome Junction to Obetsebi Lamptey Interchange) into a 2 x 3 dual carriageway. Improvement of the Awudome Road & Nii Teiko Din Street.

Phase I was executed by Messrs QGMI Construcciones E Infraestructuras Globales S.L.U with Messrs FAS Consult Ltd as the Engineer’s Representative. The Department of Urban Roads was the agency under MRH responsible for the project. Phase II according to the Ministry will commence immediately. Funding for this project, amounting to $135 million, was secured by the Akufo-Addo government and made possible by Export Credit Facilities from the United Kingdom and Spain.