The Minister of Works, Housing and Water Resources, Ahmed Ibrahim, has disclosed that six flood-control projects under the Greater Accra Resilient and Integrated Development (GARID) Project are awaiting financial authorisation from the Ministry of Finance before construction can start.
Designed to strengthen Accra’s resilience to flooding and climate-related risks, the projects are currently at the tendering and contract-award stage.
Mr Ibrahim disclosed in Parliament on Wednesday, November 18, 2026, while answering questions about the government’s efforts to address recurring floods in the capital.
The projects comprise the reconstruction of the Abbosey Okai Bridge; construction of the Atomic East and West detention ponds; improvement works on the Alajo drain; repackaging of the Nima drain works; and installation of the Accra Flood Early Warning Systems.
He said the projects could proceed only after the Ministry of Finance grants the required commitment authorisation, allowing contracts to be awarded and construction to begin.
Regarding the Nima-Paloma drainage project, Mr Ibrahim said the previous contract had been terminated. The project is to be repackaged and awarded to a new contractor once the necessary financial commitment is secured.
When the contract was terminated, progress stood at 13 per cent for evacuation of works, 25 per cent for demolition of the existing drain, 9.7 per cent for casting the concrete base and 9.5 per cent for casting the concrete walls.
He said the Ministry had engaged Dredge Masters to desilt the Nima-Paloma drain and improve stormwater flow while it sought financial clearance to continue the project.
Mr Ibrahim added that further local measures had been introduced to reduce flood exposure for communities along the upstream and downstream sections of the Nima drain.
The Ministry is also consulting relevant stakeholders, including the World Bank, to identify the appropriate procurement approach for appointing a new contractor to complete the project.